Possible Tax Burden as of 1/11/2023

The below tax burden estimates for the proposed Public Safety Complex were analyzed based on a USDA 40 year loan at 3.7% interest.  The total project cost estimates are at 5.9 million dollars, with 1 million in funding through a State Bond. The below figures are based on the 4.9 million possible taxpayer burden after subtracting the Bond funding. More funding sources are being pursued. 

These figures will be updated when new information is available. 